To create a KFS Budget Adjustment from a KC Award Budget: |
1. |
Create a new Award Budget by entering a name for the version in the Name field and then clicking the new button in the Actions column in the Budget Versions section of the Budget Versions page of the Award document. |
2. |
Click the Non-Personnel tab to display the Non-Personnel page. In the Equipment section, add an Equipment line item. In the Travel section, add a Travel line item.
|
3. |
On the Personnel page, add line items by selecting a Job Code for the person, select an Appointment Type, enter a Base Salary, and then click the [sync personnel] button which adds the person to the Award Budget as a numbered line item in the Project Personnel section.
|
4. |
In the Personnel Detail section below, select values for the Person (for example, ‘summary’), Object Code Name (for example, ‘Administrative Staff – On’) and Group (for example, new Group) fields and then click the [add] button to add your selections as a numbered line item below.
The Administrative Staff – On/new Group section appears with subsections for Group Details and Rate Classes.
|
5. |
In the subsection (line item), add a requested salary and click [calculate] to get the fringe amount displayed. This adds the calculated fringe costs to the budget.
|
6. |
Click the save
|
7. |
Navigate to the Budget Actions page, show the Data Validation section, and click the turn on validation button.
|
8. |
To fix it, go to the Parameters page of the Award Budget Document, and enter that amount (copy Budget Total Cost Limit value) in the Cost Limit Field in Budget Periods & Totals section, then click save to save this change to the document.
|
9. |
Navigate to Non-Personnel page, and select any line item that you have already added (for example, Equipment) and then click the [sync to period cost limit] button. This increases the value so it matches the total.
|
10. |
Navigate to the Budget
Actions
|
11. |
Click the save
|
12. |
Click the submit
|
13. |
While logged in to KC as
an Award Budget Approver, after the Award Budget Document has been
submitted, the Award Budget Approver opens the document from their action
list and clicks the approve button, or if the user has appropriate
permissions, the blanket approve
|
14. |
After the Award Budget document has been approved, as its Initiator, log back in to KC and open the document. Select yes to the confirmation prompt to proceed with updated rates.
|
15. |
Navigate to the Budget
Actions page. A new post
The KFS Budget Adjustment document number appears in the confirmation message in KC.
The KFS Budget Adjustment document you just created has accounting lines that match the totals in the Award Budget Summary page, and also the Budget Limits section lines in the Award (not Award Budget) document Budget Versions page (accessible via the blue [return to award] on Award Budget doc).
In KC Award doc, Budget Versions page, scroll down to Budget Limits panel , the subsection accounting lines match what is in the KFS Budget Adjustment document accounting line values, and the Object Codes for each line item expense match each other
|
End of activity. |